Case StudyVancouver WA · Full Kitchen Remodel

Kitchen Remodel in Vancouver WA: What to Expect Start to Finish

A 1970s ranch kitchen — original cabinets, failing laminate countertops, no island — documented from the first walkthrough to the final punch list. Six weeks, $28,400, and three surprises along the way.

Project Snapshot

Location

East Vancouver WA

Home Type

1970s Ranch, Slab Foundation

Kitchen Size

Approx. 220 sq ft

Total Cost

$28,400

Where We Started

The homeowners had bought the house five years earlier and lived with the original kitchen while paying down other priorities. By the time they called us, the cabinet doors had been adjusted three times and still weren't closing cleanly, the drawer slides were failing on two cabinets, and the laminate countertop near the sink had been stained through to the substrate.

They had a clear goal: full replacement, not a face-lift. New cabinets, new countertops, a quartz island they could sit at, and LVP flooring that matched the rest of the house. They'd done the research, had a $30,000 budget, and were ready to move.

The scope we agreed on: cabinet tearout and replacement, countertops, sink and faucet, island (including a prep sink with plumbing rough-in), backsplash tile, LVP flooring, LED under-cabinet lighting, and exhaust rerouting. All permitted. Six-week schedule.

Before and After: What Changed

Before

Original 1970s oak cabinets — doors misaligned, drawer slides failing

After

Full shaker-style cabinet replacement — 42" uppers, soft-close hardware throughout

Before

Builder laminate countertops with visible staining near sink

After

3cm Calacatta-look quartz with waterfall edge on the island

Before

Old drop-in stainless sink, mismatched hardware

After

Undermount composite granite sink, pull-out spray faucet, garbage disposal

Before

1970s soffit above upper cabinets — hard to clean, trapped light

After

Soffit removed, ceiling-height 42" uppers with crown moulding

Before

Worn linoleum flooring with lifting seams near the dishwasher

After

Wide-plank LVP — waterproof, continuous through to dining area

Before

No island — single L-shape with limited counter space

After

42" × 84" island with pendant lighting, seating on one side

Before

4" ceramic tile backsplash — cracked grout lines, discolored

After

3×12 subway tile in running bond from countertop to upper cabinets

Before

Under-cabinet fluorescent strip — uneven light, visible yellowing

After

LED under-cabinet puck lighting, dimmer-controlled

Week-by-Week Timeline

Week 0

Estimate & Scope

On-site walkthrough, measurements, scope document, signed contract.

Week 0–1

Material Sourcing

Cabinets ordered (3-week lead), countertop template scheduled, appliances ordered.

Week 3

Demo Day

Existing cabinets, countertops, flooring, and drywall damaged by old backsplash removed. Subfloor inspected.

Week 3

Rough-In Changes

Island plumbing rough-in, additional outlet circuit, exhaust duct rerouted.

Week 4

Cabinet Install

Upper and lower cabinets set, shimmed, and secured. Island framed and set.

Week 4

Countertop Template

Quartz countertop templated at cabinet completion. 5-day fab turnaround.

Week 5

Countertop Install

Quartz installed. Plumber sets sink and faucet same day.

Week 5

Tile & Flooring

LVP flooring installed throughout. Subway tile backsplash set and grouted.

Week 5–6

Appliances & Trim

Appliances installed. Cabinet hardware, light fixtures, outlet covers, final paint touch-up.

Week 6

Final Walkthrough

Full punch list review with homeowners. Open items addressed same week.

Three Things We Found Along the Way

Every older home has history in the walls. Here's what we found in this one and how we handled it.

Subfloor Dip Near the Dishwasher

What We Found

When the linoleum was pulled up, there was a soft spot under the dishwasher — a slow leak from a previous dishwasher drain hose had never been fully dried out. The OSB subfloor was compressed and starting to delaminate in a 12" × 18" section.

How We Handled It

We replaced the affected section of subfloor and treated the framing with a mold inhibitor. The repair added $380 to the project — we documented it with photos before closing it up, and the homeowners approved the add-on same day.

Exhaust Fan Vented Into the Attic (Not Outside)

What We Found

The existing range hood duct terminated in the attic insulation — not uncommon in 1970s builds. We discovered it when pulling the old hood. Venting into the attic deposits grease over time and can cause moisture problems in the insulation.

How We Handled It

We rerouted the duct through the exterior soffit, which added a half-day to the schedule. This is a code-required fix for any kitchen that touches the exhaust system — it was included in the scope as a contingency, so there was no surprise cost.

Island Plumbing Routing

What We Found

Adding an island prep sink required running a drain through the slab — the house was on a concrete slab foundation, not a crawlspace. The homeowners knew this going in; the scope included a contingency allowance for the core drill.

How We Handled It

Straightforward concrete core drill — no unexpected obstacles. Came in within the contingency allowance.

Where the $28,400 Went

Line ItemCost
Cabinet supply & install (42" uppers, lower run, island base)$9,200
Countertops — 3cm quartz, waterfall island edge (supply & install)$5,800
LVP flooring (supply & install, 240 sq ft)$3,100
Island construction (framing, plumbing rough-in, tile)$2,400
Subway tile backsplash (supply & install)$1,800
Sink, faucet, disposal (supply & install, both sinks)$1,600
LED under-cabinet lighting (supply & install)$900
Demo & disposal$800
Exhaust duct reroute to exterior$600
Electrical (new island circuit, GFCI outlets)$700
Permits (city, electrical)$420
Subfloor repair (contingency, actual)$380
Paint, trim, hardware$700
Total$28,400

Appliances (range, dishwasher, refrigerator) were owner-supplied and not included in the above. This project came in $1,600 under the $30,000 budget.

What the Homeowners Said

“We'd gotten quotes from two other contractors before NORBILT. The other two gave us a number with no real detail — we didn't know what was in and what wasn't. NORBILT walked us through a full written scope before we signed anything. We knew exactly what we were getting.

The subfloor issue they found under the dishwasher — that could have been a nightmare if we'd discovered it five years later. They found it, showed us photos, gave us a price to fix it the same day, and patched it before the cabinets went in. That's the kind of thing that turns a $380 repair into a $6,000 problem if you ignore it.

Six weeks felt long when we were living without a kitchen. But they hit every milestone they said they would. The final walkthrough was actually a punch list — a couple of hardware pieces and a grout line to touch up. All done within three days. We'd use them again without hesitation.”

— East Vancouver Homeowners, 2026

What to Know Before You Start Your Kitchen Remodel

Cabinets drive the schedule

Cabinet fabrication is the longest lead item — typically 2–4 weeks for semi-custom. The rest of the project is planned around cabinet delivery. Appliances have similar lead times and should be ordered before demo day so they don't become the bottleneck at installation.

Budget a contingency for older homes

Any Vancouver WA home built before 1990 has a realistic chance of subfloor moisture damage near the sink, improperly vented exhaust, or outdated electrical near the countertops. We price contingencies explicitly in the scope — not as TBD — so you know your worst-case number before we start.

Countertop template happens after cabinets are set

Quartz and stone countertops are templated after cabinets are installed, not before. This adds 5–10 days to the timeline but ensures a precise fit. Plan for a period of a few days without a countertop — it's normal and expected.

You'll be without a kitchen for 2–4 weeks of active work

Plan for limited kitchen access. Most homeowners set up a microwave and mini-fridge in another room, lean on a grill, and treat it as an opportunity to try takeout spots they've been meaning to visit.

Don't sequence appliances last

Appliance installation at the end of a project can expose delays in your supply chain that you can't control. Order appliances when you sign the contract — not when the cabinets are in.

Ready to start your kitchen remodel in Clark County?

View our full kitchen remodel service — scope, process, warranty, and what to expect in Vancouver and Clark County.

Kitchen Remodel Service

Kitchen Remodel FAQ — Vancouver WA

How long does a full kitchen remodel take in Vancouver WA?

A full kitchen remodel in Vancouver WA typically takes 4–7 weeks from demo to final walkthrough. The longest wait is usually cabinet fabrication (2–4 weeks) and countertop fabrication after templating (5–10 days). Structural or plumbing changes add time. Plan for 3–4 weeks of limited kitchen access during the active work phase.

How much does a full kitchen remodel cost in Vancouver WA?

A full kitchen remodel in Vancouver WA costs $18,000–$45,000+ depending on cabinet quality, countertop material, appliances, and whether layout changes are involved. A mid-range remodel — new cabinets, quartz countertops, standard appliances, tile backsplash, and LVP flooring — runs $22,000–$32,000. See our kitchen remodel cost guide for Vancouver WA for a full price breakdown.

What surprises should I expect during a kitchen remodel?

The most common surprises in older Vancouver WA homes are subfloor moisture damage (especially near the sink or dishwasher), improperly vented range hoods, outdated electrical (no GFCI near the sink, undersized circuits for modern appliances), and asbestos floor tile under linoleum in pre-1980 homes. A good contractor identifies these during the estimate, documents them during demo, and prices contingencies upfront rather than billing surprises mid-project.

Do I need a permit for a kitchen remodel in Vancouver WA?

You need a permit for any kitchen remodel that moves plumbing, adds or modifies electrical circuits, or makes structural changes (removing a wall, relocating a window). Cabinet replacements, countertop swaps, and appliance upgrades without any of those changes typically don't require a permit. NORBILT (WA Lic. NORBI**741CS) handles all permitting for any permitted scope — fees are included in the bid.

Should I stay home during a kitchen remodel?

It's your call. Most homeowners with children or pets prefer to be home on demo day and available during the first week. After that, with a locked door code and a daily check-in message, many homeowners go about normal routines. We set expectations at the start: what days we're on site, when we're not, and how to reach us for anything urgent.

Licensed · WA Lic. NORBI**741CS · Clark County

Get a Free Kitchen Remodel Estimate

We walk the kitchen, take measurements, identify any visible risk areas (subfloor, exhaust, electrical), and give you a written scope and price before anything starts. Same-week availability for Vancouver and Clark County homeowners.

Call Now Get Instant Estimate